Building Renovations
Elevator Update
The building's main elevators, located behind the Information Desk on the 1st floor, are undergoing renovations. Car 1 is up and running, while car 2 is still undergoing construction.
Staircases can also be accessed throughout the building. Look for the main staircase in the atrium next to the information desk, the staircase just inside the east entrance, and the staircase next to Blenz Bowls will take you all the way to the 4th floor.
Construction Begins
August 11
Renovations begin on elevator 1 with an expected completion date in early November. Renovations on elevator 2 will begin upon completion of elevator 1.
Car 1: Ready for Framing
September 9

A look inside the elevator shafts. Car 1 shaft is empty and ready for the new system framing to be installed.
Car 1: Hoist Update
October 7

Restructuring and engineering of the hoist way to accommodate a larger and more efficient elevator.
New Car 1
October 7

The new cab interior is complete with finished walls. The upgraded car features a smoother and quieter operation.
Car 1: Up and Running!
December 15

Car 1 is officially back in operation and work has begun on Car 2.
Car 2: Under Construction
January 5

Elevator 2 is not in service while construction is in progress.